Milverton/Drexmore Waterline/Street Resurfacing (last update: 4/11/08):
Anticipated completion: July 3, 2008
  • Waterline placement has begun.

Ramona Lowery, Sewer Superintendent/Project Manager, 216-491-3297

Relining of Culvert at North Park Boulevard and Eaton Road (last update: 4/11/08)
Anticipated completion date: March 28, 2008

  • The project is complete except for the grass areas -- restoration will be performed in the spring.

Karrie L. Buxton, Project/Construction Manager, 216-491-3283.

Soccer Fields (last update: 4/11/08)

Shaker Median (Installation of new field):
Anticipated completion: April 2008

  • Completion of construction road across practice field area and drainage system.
  • Electrical work continued for traffic light on Shaker Blvd.– tunneling beneath Shaker began April 7.
  • Giving field a chance to dry out.

Chesterton, Courtland Oval and Shaker Town Center (Restoration):
Anticipated completion: weather permitting

  • Chesterton: Installation of top soil and seeding begun.

Bill Murray, Manager, Thornton Park and Facilities, 216-491-2586