In mid-June, a water main replacement project gets underway on Aldersyde Rd. between Lee and Onaway roads. The project is scheduled for completion by the end of September (weather permitting). Please note:
- Traffic is local access only for the duration of the project; motorists should seek alternate routes.
- Street parking will be prohibited from 7 am to 5 pm.
- Trash and recycling collection schedules will remain the same.
- Public Works and the contractor will be coordinating with the High School throughout the project to minimize inconveniences.
Work hours are 7:30 am to 3:30 pm. Impacted residents will receive notification from the contractor prior to the project's start date. Residents observing any vandalism at the construction site should call the Shaker Heights Police Dept. at 216-491-1234.
For questions about the project, please contact Construction Manager Christian Maier at 216-491-1490.