Phase 2 Road Resurfacing Starts Week of June 19

Graphic for construction update notice

Phase 2 of the City's 2023 road resurfacing program starts the week of June 19. The following streets will be repaved during this phase. Anticipated completion is mid-August (weather permitting). Impacted residents will receive a notification from the City before work starts.

PHASE 1: MID-APRIL TO EARLY JUNE
Leighton RoadLarchmere to Shaker
West Belvoir RoadShaker to S. Woodland
Sydenham RoadByron to W. Belvoir Oval
Avalon RoadFernway to Aldersyde
Torrington RoadShaker to S. Woodland
Shelburne RoadEaton to Courtland
Holbrook RoadStockholm to Elsmere


Scope of Work

The phases for resurfacing a street are:

  • Phase I:  Removal of existing asphalt pavement & placement of new intermediate asphalt
  • Phase II:  Adjustment of catch basin and manholes, replacement of select driveway aprons and installation of new ADA curb ramps (as necessary). 
  • Phase III:  Placement of the surface asphalt course
  • Phase IV:  Pavement markings

Guidelines During Resurfacing

  • No on-street parking permitted between 7 am and 7 pm
  • Residents should avoid blowing leaves into the street during resurfacing. 
  • Residents whose driveway aprons are being replaced should contact the Police Department (216.491.1220.) or use the online form to request overnight parking on the street. .
  • Please observe all signs, barricades and warning lights.. 
  • Also, please help keep neighborhood children safe by warning them about the danger of playing in the construction site or on any of the equipment. 

We know that having a construction project on your street is an inconvenience. Thank you in advance for your patience and understanding.

 Questions? Contact Christian Maier, Assistant Public Works Director, at 216-491-1490 or by email