The City plans to begin its 2019 street resurfacing projects in mid-April (weather permitting). Construction is anticipated to take 100 calendar days (also weather permitting). The City will provide updates as the schedule is finalized.
This year, the following streets are scheduled to be resurfaced:
PHASE 1
|
|
|
---|
Street | Limits | Area (SY) |
Coventry Road | S. Park - Northern Corp. | 3300 |
Claythorne Road | Brantley - Shelburne | 3264 |
Chadbourne Road | Southington - Onaway | 5278 |
Glencairn Road | Van Aken - Chagrin | 2431 |
Sutton Road | Van Aken - Milverton | 1389 |
Tolland Road | Norwood - Scottsdale | 5000 |
Menlo Road | Rife Ct. - Scottsdale | 5833 |
Farnsleigh Road | Helen - Van Aken | 6667 |
Winslow Ct. | Avalon | 1283 |
PHASE 2
|
|
|
---|
Street
| Limits | Area (SY) |
Huntington Road | Coventry - Onaway | 10,417 |
Avalon Road | Fernway - Van Aken | 4931 |
Strathavon Road | Lomond - Scottsdale | 4306 |